Metso Outotec to deliver rotary kiln system for Lynas Kalgoorlie’s greenfield project in Western Australia

Metso long kiln
© Metso Outotec

Metso long kiln
© Metso Outotec
Metso Minerals has signed a contract with Lynas Kalgoorlie Pty Ltd for the supply of a large rotary kiln and combustion system for baking rare earth elements. The order value of approximately € 13 million has been booked in Metso Minerals’ Q2 2020 orders received. Commissioning of the kiln is expected to take place in 2022.

Commenting on the award, Lynas CEO and Managing Director Amanda Lacaze said: “The kiln is the longest lead time item for our Kalgoorlie project and placing this order is an important milestone in the development of our new processing plant in Kalgoorlie. The project is progressing to schedule and we look forward to working with Metso Outotec on the engineering and supply of the kiln.”

Lynas is the second largest producer of rare earths and the largest outside of China. Metso Outotec is a leader in the supply of rotary kilns for the mining industry, with over 1300 installations worldwide. The companies will work together to develop a rotary kiln system for Lynas’ new greenfield cracking & leaching plant in Kalgoorlie-Boulder, Western Australia. The plant will process concentrate from the Mount Weld mine and provide an intermediate feed for further processing to produce NdPr (neodymium and praseodymium), which are key elements used in high-tech consumer electronics and green energy technologies.

“We are excited at having been selected by Lynas as a key supplier for the development of its significant greenfield project in Western Australia. Metso Outotec’s rotary kiln system forms an integral part for the processing of rare earths,” says Stephan W. Kirsch, President, Minerals business area, Metso Outotec.

www.@mogroup.com

Related articles:

Approvals for the combination of Metso Minerals and Outotec

Metso Corporation (“Metso”) and Outotec Oyj (“Outotec”) have received the remaining outstanding competition clearances for the combination of Metso’s Minerals business with Outotec through a...

more

Metso Outotec wins order for large iron ore pellet plant in Oman

Metso Outotec has signed an agreement for the delivery of engineering and key equipment for an iron ore Grate Kiln pellet plant to Vulcan Pelletizing LLC. The plant is located in the industrial port...

more
2021-10

Metso Outotec to deliver water treatment plant for a gold mine

Metso Outotec has signed an engineering and technology contract to deliver a raw water treatment plant for a gold plant project in the Middle East. The order value exceeds € 10 million, and it has...

more

Metso Outotec awarded order for key technology to Boliden’s Green Zinc Odda project in Norway

Metso Outotec has been awarded a contract for the delivery of key technology to the Boliden Odda zinc smelter expansion in western Norway. Approximately ninety percent of the € 150 million contract...

more

Metso Outotec wins major order for siderite calcination plant in Turkey

Metso Outotec has signed an agreement for the delivery of a siderite calcination plant to Hekimhan Madencilik, a subsidiary of Kolo?lu Holding, located in Malatya/Turkey. The value of the order is...

more